Main data:

Total height: 98 m
Number of floors: 29
Planned term of finishing: 2010
Designer: M. Podbielski, P. Cichocki, A. Skolimowska, I. Szostak, P. Wodzisławski
Location: ul. Grzybowska 45

In 2005 on south-western corner of Grzybowska and Zelazna intersection the construction of the complex called Centrum Zelazna began. Before Second World War buildings of the brewery Haberbusch and Schiele used to stand here. First, two lower, 7-storyed buildings, which continue the frontage of Zelazna street, were constructed, and also two higher, 15-storyed, situated behind them. And in 2007 the construction of a skyscraper called JM Tower was started.

The investment is carried out by developer JM Property. In the underground a car park for 135 cars will be located. Higher, up to 15th floor, there will be offices to rent, and on top floors - hotel rooms. Apart from that, also some shops are planned to by organised in the building. Altogether, the building will have 27 thousand metres of area (from which 14 thousand will be offices).

The building will be a simple, straight solid, just like other surrounding skyscrapers: Hilton, PKO or yet not finished Platinum Towers.

The skyscraper is being constructed for more than a year by now, today (October 2009) last floors are under construction. The building rises slowly, but systematically - in contrast to for example Zlota 44 by Orco, which was previously growing up faster.

The building's visualisations:

A future view from Zelazna street A view from the intersection of Zelazna and Grzybowska street A view from John Paul II Avenue A view from the back (from the area of Lucka street) The new skyscraper in Warsaw's night panorama

Photos of the skyscraper's building site:

Pictures taken on 29th of May 2008:

The building on the corner of Zelazna and Grzybowska (also a part of Zelazna Centrum complex), on the right - the skyscraper's construction The skyscraper's building site - for now, only the structure of a few floors is finished A view on the building site from the north

Pictures taken on 26th of October 2008:

A view from the back (from Lucka street) A view from the intersection of Grzybowska and Walicow streets Now the structure of about 10 floors is finished A view from the intersection of Grzybowska and Zelazna A view from the front A view from the western side (from the backyard of houses at Grzybowska street

Pictures taken on 16th of December 2008:

After 2 months the structure is only about 2 floors higher A view from the north-western side A view from the intersection of Zelazna and Grzybowska streets A view from the backyard at Lucka street

Pictures taken on 10th and 15th March 2009:

The construction reached 17th floor The skyscraper is already nearly as high as the neighbouring Pekao SA building A view from the intersection of Zelazna and Grzybowska A view from north-western side One more view from north-west A view from a distance A view of last floors

Pictures taken on 4th of May 2009:

The structure reached about 20 floors what is more than 2/3 of the final height A view from north-eastern side A view from north-western side A view from the close One more view from north-western side A view from Grzybowska street A close-up of the upper-part

Pictures taken on 22nd of July 2009:

The structure has now about 25 floors, only a few are lacking A view from north-eastern side A view from the intersection of Zelazna and Grzybowska streets A view from Zelazna street, on the right a fragment of ruined pre-war house at Zelazna no. 65 A view from northern side A view from north-western side Another view from north-west A view from Grzybowska street, on the right a fragment of Pekao SA skyscraper A view from Wronia street One more view from north-eastern side A view from Zelazna street

Pictures taken on 1st of August 2009:

A view from western side A view from south-western side One more view from south-western side A view from the intersection of Zelazna and Pereca streets A view from Zelazna street (from south-eastern side) A view from Grzybowska street Contrasts typical for Wola district A newly-built skyscraper and in front of it: some rought-and-ready housed at the backyards at Lucka street The JM Tower's construction seen from the close

Pictures taken on 13th of October 2009:

A view from Zelazna street (next to former Norblin factory) A view from the intersection of Pereca and Zelazna streets A view from south-western side A view from western side One more view from western side A view from Grzybowska street A view from northern side A view from north-eastern side A view from eastern side (from Grzybowska street) A view from north-eastern side (from Zelazna street) Last floors are being constructed, the building clearly dominates Grzybowska street now One more view from Grzybowska street

Pictures taken on 23rd and 24th of January 2010:

On most floors windows have been installed A view from the area of the intersection of Zelazna and Ogrodowa streets A view from Zelazna street, next to Krochmalna street Another view from Zelazna street A view from the intersection of Zelazna and Grzybowska streets A view from the close A view from Grzybowska street A view from the southern side (from Zelazna street) A view from the intersection of Zelazna and Pereca A view from south-western side A view from the western side A view from Prosta street A view from the southern side (from a backyard at Lucka street)

Pictures taken on 2nd of April 2010:

On the southern side windows has already been installed on all floors A view from Zelazna street (from the area of Norblin) On the western side the construction on which elevation will be installed already appeared The western wall of the building A view from Grzybowska street A close-up of the upper-part (the western wall) One more close-up of the western wall, elevation is being installed here On the northern side windows are not yet everywhere A fragment of the northern wall (from Grzybowska street)

Pictures taken on 23rd and 26th of April 2010:

On the western wall still the elevation is being installed A view from the northern side A view from Zelazna street (from north-eastern side) One more view from north-eastern side A view from Grzybowska street (from the eastern side) North-eastern corner of the building A view from the intersection of Zelazna and Pereca streets A view from Zelazna street (north-eastern corner of the building) The eastern wall North-eastern corner The eastern wall - the elevation is being put A close-up of the eastern wall - first fragments of the elevation appeared

Pictures taken on 20th and 21st of May 2010:

Installing the elevation on the eastern wall of the building Zachodnia ściana budynku już w docelowej kolorystyce Szczyt wschodniej ściany Układanie elewacji w dolnej części wschodniej ściany Elewacja na zachodniej ścianie też już w dużej mierze ułożona Widok od strony północno-zachodniej Południowo-wschodni narożnik Wschodnia ściana (widok z ulicy Żelaznej) Widok z ulicy Grzybowskiej (od strony wschodniej) Widok od strony północno-wschodniej Widok od strony ulicy Łuckiej Widok od strony północno-zachodniej Widok od strony południowo-zachodniej